Since the commencement of works in July 2009, the construction of West Island Line is in full swing.
Progress of tunnelling works by blasting method (PDF)
All TBM works was completed in Nov 2012

Contract Awarded

Contract No. Contract Name Contractor Contract Award Date Completion Date Construction Sites
701 Modification of Sheung Wan Station 701

Progress of work

Sun Fook Kong Construction Ltd 04/2010 08/2012 Completed
  Last Updated at : March 2013
 
  • Sheung Wan Station Modification works for the Sheung Wan Station have been completed. New public toilet facilities and two new lifts were opened for service on 26 August 2012.
703 Sheung Wan-to-Sai Ying Pun Tunnel Construction 703

Progress of work

Dragages - Maeda - BSG Joint Venture 08/2009 2013
  • Sai Woo Lane & Queens Road West
  • New Market Street
  • Ko Shing Street,
    Li Sing St &
    Des Voeux Road West
  Last Updated at : March 2013
 
  • Sai Woo Lane & Queen's Road West At Sai Woo Lane site, structural work for the south shaft has started on Sai Ying Pun Station entrance at Queen’s Road West. Excavation in the north shaft is being carried out for the construction of Sai Ying Pun Station entrance at Des Voeux Road West.

  • New Market Street The New Market Street grouting works have been completed. The road section was temporarily re-opened in February 2012 and the final reinstatement works will proceed in the second quarter of 2013.

  • Ko Shing Street, Li Sing St & Des Voeux Road West Dismantling works for Sheung Wan Station overrun tunnels was completed in October 2012. At Ko Shing Street, the existing vent shaft was back filled and ventilation system will be removed in February 2013. Mechanical plant along Des Voeux Road West were removed. The associated road reinstatement and drainage works are expected to complete in the second quarter of 2013 together with the re-opening of Ko Shing Street.
704 Sai Ying Pun and Hong Kong University Station, and Sai Ying Pun to Kennedy Town Tunnel Construction 704

Progress of work

Gammon Nishimatsu WIL Joint Venture 03/2010 2014
  • King George V Memorial Park
  • Ex-David Trench Rehabilitation Centre
  • Ex-Centre Street Cooked Food Centre
  • Ki Ling Lane Children's Playground
  • Haking Wong Building, HKU
  • Ex-Whitty Street Public Toilet
  • Pokfulam Road next to Yam Pak Building, HKU
  • Belcher's Street Sitting-out Area
  • Hill Road
  • Western District Public Cargo Working Area
  • Kennedy Town Praya Shaft
  • Victoria Road
  Last Updated at : March 2013
 

  • King George V Memorial Park Blast excavations are being carried out underground at the King George V Memorial Park work site.

  • King George V Memorial Park Blasting for passenger adits is on-going underneath Second Street, Third Street, Eastern Street and Bonham Road. It is expected blasting to be completed around the second quarter of 2013.

  • Ex-David Trench Rehabilitation Centre Shaft excavation works are being carried out for the construction of SYP station entrance at Bonham Road.

     

     

     


  • Ex-Centre Street Cooked Food Centre Shaft excavation works are ongoing for the construction of one of the Sai Ying Pun station entrances. The construction of decking to cover the work site is completed.

     

     

  • Ki Ling Lane Children’s Playground Structural works of SYP station entrance are in progress. The passenger adit will be constructed by ground freezing technique and the associated freezing units are installed within a noise enclosure.
  • Haking Wong Building, HKU Shaft excavation works were completed and structural works have started at the base of the shaft to form the entrance of Hong Kong University Station.
  • Ex-Whitty Street Public Toilet Excavation works are taking place for the construction of a passenger adit and one of the Hong Kong University Station entrances. To minimize the excavation works impacts to the nearby buildings, decking has been placed to cover most of the site area.
  • Pok Fu Lam Road next to Yam Pak Building, HKU Shaft excavation works were completed and structural works have started within the shafts to form the entrance.
  • Belcher’s Street Sitting-out Area Structural works, road reinstatement and drainage works of the Hong Kong University station entrance are in progress.

  • Hill Road Excavation of the Hong Kong University Station entrance and passenger adit is in progress.
  • Kennedy Town Praya Shaft The track laying works for the up-track railway tunnel from Kenney Town station toward Hong Kong University station have completed while the works at the down-track railway tunnel are in progress.

  • Western District Public Cargo Working Area The two temporary tipping halls continue to operate to ship away excavated materials by sea. The fully-enclosed conveyor belt will be demolished in stages in April and May 2013.

  • Victoria Road – Temporary Underground Magazine Site Temporary Underground Magazine continues to be in operation for storage of explosives for WIL blasting works.
705 Kennedy Town Station and Overrun Tunnel Construction 705

Progress of work

Gammon Construction Ltd 12/2009 2014
  • Ex-Kennedy Town Swimming Pool
  • Forbes Street Playground
  • Sands Street
  • Sai See Street
  • Kennedy Town Ex-Police Quarter
  Last Updated at : March 2013
 
  • Ex-Kennedy Town Swimming Pool Construction of the Kennedy Town Station structure is being carried out. Station platform structural works and track laying works are completed. The works are covered with noise decking so as to minimize the noise and dust nuisance.
  • Forbes Street Playground Construction of the Kennedy Town Station box at the Forbes Street work site is nearly complete. Structural works for the station entrance and ventilation facilities are in progress.
  • Sands Street
    The construction of the escalator and lifts at Sands Street was completed and the facilities were available for public use on 27 December 2012. Meanwhile, the pavement widening works and road reinstatement works at Rock Hill Street are in process.
  •  
  • Kennedy Town Ex-Police Quarter Track laying works and ventilation shaft construction works are in progress at Kennedy Town overrun tunnel.
706 Access Shafts at Kennedy Town Praya and Hill Road Paul Y. Construction Company Ltd 07/2009 2010 Completed
  Last Updated at : December 2012
 

  • Hill Road
    Excavation works are in progress.
706A Slope Upgrading and Natural Terrain Mitigation Works Paul Y Construction Company Ltd 11/2009 2/2011 Completed
  Sheung Wan-to-Sai Ying Pun Tunnel Construction
Blasting works were successfully completed. Electrical and mechanical works are in progress
Last Updated at : March 2010
708 Temporary Underground Magazine Construction Gammon Construction Ltd 07/2009 2010 Completed
  Last Updated at : June 2012
 

  • Victoria Road
    Blasting works have been successfully completed. Electrical and mechanical works are in progress.
710 Re-provisioning of Kennedy Town Swimming Pool (Phase I) 710

Progress of work

Paul Y Construction Company Ltd 07/2009 03/2011 Completed
  Last Updated at : March 2013
 

  • Kennedy Town Praya Re-provisioning of Kennedy Town Swimming Pool (Phase I) was completed and the swimming pool was opened to the public in May 2011.
711 Re-provisioning of David Trench Rehabilitation Centre 711

Progress of work

Sun Fook Kong Construction Ltd 07/2009 03/2011 Completed
  Last Updated at : March 2013
 

  • Ex-Upper Level Police Station Re-provisioning of David Trench Rehabilitation Centre was completed. The Centre was handed over to the Hospital Authority and started to provide services to the public in April 2011.
714 Project Site Office and Works Area Sun Fook Kong Construction Ltd 07/2009 2010 Completed
  Sheung Wan-to-Sai Ying Pun Tunnel Construction
Rail track and overhead line components are being delivered to Siu Ho Wan Depot for temporary storage.
Last Updated at : October 2011
715 Trackwork and Overhead Line715

Progress of work

Eiffage Rail-Tak Yue Joint Venture 12/2010 2014
  • Kennedy Town Overrun Tunnel
  • Sai Ying Pun and Sheung Wan Tunnels
  Last Updated at : March 2013
 
  • Various Locations The track laying works are being carried out at down-track railway tunnel from HKU station toward KET station and HKU station platform. To facilitate the E&M works, two sets of works trains are in operation at the lower level of the Kennedy Town worksite. E&M works inside the HKU Station have commenced.
716 Instrumentation and Monitoring Lam Geotechnical Limited 10/2009 2014 N/A
  Sheung Wan-to-Sai Ying Pun Tunnel Construction
Blasting works were successfully completed. Electrical and mechanical works are in progress
Last Updated at : June 2012
7201 Tree Transplanting Yee Sun Garden Ltd. 07/2009 2010 Completed
  Sheung Wan-to-Sai Ying Pun Tunnel Construction
Blasting works were successfully completed. Electrical and mechanical works are in progress
Last Updated at : June 2012
C6554-07E Rolling Stock Changchun Railway Vehicles Co. Ltd. 10/2008 12/2011 N/A
  Sheung Wan-to-Sai Ying Pun Tunnel Construction
Blasting works were successfully completed. Electrical and mechanical works are in progress
Last Updated at : June 2012
752 Signalling System Alstom Hong Kong Ltd 10/2010 2014 N/A
  Alstom Hong Kong Ltd
Blasting works were successfully completed. Electrical and mechanical works are in progress
Last Updated at : June 2012
753 Trackside Auxiliaries and Environmental Control System ATAL Engineering Limited 03/2011 2014 N/A
  Alstom Hong Kong Ltd
Blasting works were successfully completed. Electrical and mechanical works are in progress
Last Updated at : June 2012
754 Platform Screen Door System KABA GILGEN AG 10/2010 2014 N/A
  Sheung Wan-to-Sai Ying Pun Tunnel Construction
Blasting works were successfully completed. Electrical and mechanical works are in progress
Last Updated at : June 2012
755 Power Supply System GTECH-Paul Y. Joint Venture 01/2011 2014 N/A
  Sheung Wan-to-Sai Ying Pun Tunnel Construction
Blasting works were successfully completed. Electrical and mechanical works are in progress
Last Updated at : June 2012
757 Lifts KONE Elevator (HK) Ltd 12/2010 2014 N/A
  Sheung Wan-to-Sai Ying Pun Tunnel Construction
Blasting works were successfully completed. Electrical and mechanical works are in progress
Last Updated at : June 2012
758 Escalators and Moving Walkways KONE Elevator (HK) Ltd 12/2010 2014 N/A
  Sheung Wan-to-Sai Ying Pun Tunnel Construction
Blasting works were successfully completed. Electrical and mechanical works are in progress
Last Updated at : June 2012
759 Main Control System Thales Transport & Security (Hong Kong) Ltd 01/2011 2014 N/A
  Sheung Wan-to-Sai Ying Pun Tunnel Construction
Blasting works were successfully completed. Electrical and mechanical works are in progress
Last Updated at : June 2012
760 Communications, Transmission & Telephone Systems CLPE-SHSI Joint Venture 01/2011 2014 N/A
  Sheung Wan-to-Sai Ying Pun Tunnel Construction
Blasting works were successfully completed. Electrical and mechanical works are in progress
Last Updated at : June 2012
761 Radio System Radio Frequency Engineering Ltd 12/2010 2014 N/A
  Sheung Wan-to-Sai Ying Pun Tunnel Construction
Blasting works were successfully completed. Electrical and mechanical works are in progress
Last Updated at : June 2012
771 Building Services for Sai Ying Pun Station and Hong Kong University Station Gammon E&M Ltd 10/2010 2014 Sai Ying Pun Station and Hong Kong University Station
  Sheung Wan-to-Sai Ying Pun Tunnel Construction
Blasting works were successfully completed. Electrical and mechanical works are in progress
Last Updated at : June 2012
771B Building Services for Kennedy Town Station Chun Wo E&M Engineering Ltd 10/2010 2014 Kennedy Town Station
  Sheung Wan-to-Sai Ying Pun Tunnel Construction
Blasting works were successfully completed. Electrical and mechanical works are in progress
Last Updated at : June 2012
772 Trainborne Signalling Equipment Alstom Hong Kong Ltd. 04/2009 12/2011 N/A
  Sheung Wan-to-Sai Ying Pun Tunnel Construction
Blasting works were successfully completed. Electrical and mechanical works are in progress
Last Updated at : June 2012