Since the commencement of works in July 2009, the construction of West Island Line is in full swing.
Progress of tunnelling works by blasting method
Progress of tunnelling works by TBM

Contract Awarded

Contract No. Contract Name Contractor Contract Award Date Completion Date Construction Sites
701 Modification of Sheung Wan Station 701

Progress of work

Sun Fook Kong Construction Ltd 04/2010 2012
  • Sheung Wan Station
  Last Updated at : April 2012
 
  • Sheung Wan Station Modification works for the Sheung Wan Station are being carried out in stages, currently the lift connecting the concourse level and street level is under construction. The new east concourse of Sheung Wan Station and entrance/exit E3 were open for service on 13 November 2011.
703 Sheung Wan-to-Sai Ying Pun Tunnel Construction 703

Progress of work

Dragages - Maeda - BSG Joint Venture 08/2009 2013
  • Sai Woo Lane & Queens Road West
  • New Market Street
  • Ko Shing Street,
    Li Sing St &
    Des Voeux Road West
  Last Updated at : April 2012
 
  • Sai Woo Lane & Queen’s Road West The Tunnel Boring Machine (TBM) has completed the excavation of the up-track tunnel from Sai Woo Lane to Sheung Wan Station. Another set of TBM components is being delivered to Sai Woo Lane work site in stages for assemble, to prepare for the boring of the down-track tunnel. Excavation of the South Shaft is ongoing while vertical blasting of the shaft at Sai Woo Lane work site for the station entrance of Sai Ying Pun is planned to commence in May 2012 and complete in September 2012. Blasting works will be conducted up to two times per week under decking so as to minimize the impacts to nearby residents.

  • New Market Street The New Market Street grouting works were completed in January 2012. The road section has been temporarily re-opened in February 2012, and the road maintenance and reinstatement works will be carried out in end 2012 or early 2013.
  • Ko Shing Street, Li Sing St & Des Voeux Road West Demolition work of the Sheung Wan Station Overrun Tunnel will be carried out by Tunnel Dismantling Machine. Components of the machine have been delivered to the underground overrun tunnel and assembled. The machine will start the dismantling works in May 2012.
704 Sai Ying Pun and Hong Kong University Station, and Sai Ying Pun to Kennedy Town Tunnel Construction 704

Progress of work

Gammon Nishimatsu WIL Joint Venture 03/2010 2014
  • King George V Memorial Park
  • Ex-David Trench Rehabilitation Centre
  • Ex-Centre Street Cooked Food Centre
  • Ki Ling Lane Children's Playground
  • Haking Wong Building, HKU
  • Ex-Whitty Street Public Toilet
  • Pokfulam Road next to Yam Pak Building, HKU
  • Belcher's Street Sitting-out Area
  • Hill Road
  • Western District Public Cargo Working Area
  • Kennedy Town Praya Shaft
  • Victoria Road
  Last Updated at : April 2012
 

  • King George V Memorial Park Blast excavations are being carried out underground at the King George V Memorial Park work site.

  • King George V Memorial Park Blast excavations are being carried out underneath Second Street, Third Streets, High Street, Centre Street and Bonham Road for the construction of Sai Ying Pun station cavern.

  • Ex-David Trench Rehabilitation Centre Foundation works are completed while excavation for the Sai Ying Pun station entrance is in progress.

     

     

     


  • Ex-Centre Street Cooked Food Centre Foundation works are on-going for the construction of the Sai Ying Pun station entrance.

     

     


  • Ki Ling Lane Children’s Playground Structure works are in progress for the construction of the Sai Yin Pun station entrance.
  • Haking Wong Building, HKU Shaft excavation works underneath a noise deck are in progress for the construction of an entrance of the Hong Kong University Station.
  • Ex-Whitty Street Public Toilet Excavation and slope stabilizing works for the construction of passenger adit and one of the Hong Kong University Station entrances are in progress.
  • Pokfulam Road next to Yam Pak Building, HKU Excavation works for two vertical shafts are in progress for construction of an entrance of the Hong Kong University Station and ventilation shaft.
  • Belcher’s Street Sitting-out Area Construction of the Hong Kong University Station entrance structure is in progress.

  • Hill Road Excavation of the passenger adit connecting Whitty Street entrance to Hong Kong University Station is in progress.
  • Kennedy Town Praya ShaftUnderground blast excavation for Hong Kong University station cavern is in progress. The running tunnel excavation between Hong Kong University Station and Sai Ying Pun Station is now completed while the tunnel lining works has been commenced.

  • Western District Public Cargo Working Area The enclosed temporary stockpile area and two temporary tipping halls are now in operation to ship away excavated materials. The fully enclosed conveyor belt is also in operation.

  • Victoria Road – Temporary Underground Magazine Site Temporary Underground Magazine is in operation for storage of explosives for WIL blasting works.
705 Kennedy Town Station and Overrun Tunnel Construction 705

Progress of work

Gammon Construction Ltd 12/2009 2014
  • Ex-Kennedy Town Swimming Pool
  • Forbes Street Playground
  • Sands Street
  • Sai See Street
  • Kennedy Town Ex-Police Quarter
  Last Updated at : April 2012
 
  • Ex-Kennedy Town Swimming Pool Traffic deck installation was completed and excavation works are being carried out at the Ex-Kennedy Town Swimming Pool site for the construction of the Kennedy Town Station.
  • Forbes Street Playground Excavation of the overrun tunnel adjacent to the basketball court has been completed, and the construction of the concrete tunnel lining has commenced. The construction of the Forbes Street station box is well underway with sections of the station structures already casted.

  • Sands StreetComponents of Sands Street escalator is being delivered for assembling. The steel frame of lift pit at Rock Hill Street is under construction.

  • Sai See Street (ex-abattoir & ex-incinerator site ) The temporary barging point at Sai See Street is in operation to ship the excavated materials off-site.
  • Kennedy Town Ex-Police QuarterThe breakthrough of the Kennedy Town overrun tunnel took place in February 2012 and the construction of the concrete tunnel lining is in progress.
706 Access Shafts at Kennedy Town Praya and Hill Road Paul Y. Construction Company Ltd 07/2009 2010 Completed
  Last Updated at : April 2012
 

  • Hill Road
    Excavation works are in progress.
706A Slope Upgrading and Natural Terrain Mitigation Works Paul Y Construction Company Ltd 11/2009 2/2011 Completed
  Sheung Wan-to-Sai Ying Pun Tunnel Construction
Blasting works were successfully completed. Electrical and mechanical works are in progress
Last Updated at : March 2010
708 Temporary Underground Magazine Construction Gammon Construction Ltd 07/2009 2010 Completed
  Last Updated at : April 2012
 

  • Victoria Road
    Blasting works have been successfully completed. Electrical and mechanical works are in progress.
710 Re-provisioning of Kennedy Town Swimming Pool (Phase I) 710

Progress of work

Paul Y Construction Company Ltd 07/2009 2011 Completed
  Last Updated at : April 2012
 

  • Kennedy Town Praya Re-provisioning of Kennedy Town Swimming Pool (Phase I) was completed and the swimming pool was opened to the public in May 2011.
711 Re-provisioning of David Trench Rehabilitation Centre 711

Progress of work

Sun Fook Kong Construction Ltd 07/2009 2011 Completed
  Last Updated at : April 2012
 

  • Ex-Upper Level Police Station Re-provisioning of Kennedy Town Swimming Pool (Phase I) was completed and the swimming pool was opened to the public in May 2011.
714 Project Site Office and Works Area Sun Fook Kong Construction Ltd 07/2009 2010 Completed
  Sheung Wan-to-Sai Ying Pun Tunnel Construction
Rail track and overhead line components are being delivered to Siu Ho Wan Depot for temporary storage.
Last Updated at : October 2011
715 Trackwork and Overhead Line715

Progress of work

Eiffage Rail-Tak Yue Joint Venture 12/2010 2014
  • Siu Ho Wan Depot
  Last Updated at : April 2012
 

  • Siu Ho Wan Depot Rail track and overhead line components are being delivered to Siu Ho Wan Depot for temporary storage.
716 Instrumentation and Monitoring Lam Geotechnical Limited 10/2009 2014 Various locations
  Sheung Wan-to-Sai Ying Pun Tunnel Construction
Blasting works were successfully completed. Electrical and mechanical works are in progress
Last Updated at : April 2012
7201 Tree Transplanting Yee Sun Garden Ltd. 07/2009 2010 Completed
  Sheung Wan-to-Sai Ying Pun Tunnel Construction
Blasting works were successfully completed. Electrical and mechanical works are in progress
Last Updated at : April 2012
C6554-07E Rolling Stock Changchun Railway Vehicles Co. Ltd. 10/2008 12/2011 N/A
  Sheung Wan-to-Sai Ying Pun Tunnel Construction
Blasting works were successfully completed. Electrical and mechanical works are in progress
Last Updated at : April 2012
752 Signaling System Alstom Hong Kong Ltd 10/2010 2014 N/A
  Alstom Hong Kong Ltd
Blasting works were successfully completed. Electrical and mechanical works are in progress
Last Updated at : April 2012
753 Trackside Auxiliaries and Environmental Control System ATAL Engineering Limited 03/2011 2014 N/A
  Alstom Hong Kong Ltd
Blasting works were successfully completed. Electrical and mechanical works are in progress
Last Updated at : April 2012
754 Platform Screen Door System KABA GILGEN AG 10/2010 2014 N/A
  Sheung Wan-to-Sai Ying Pun Tunnel Construction
Blasting works were successfully completed. Electrical and mechanical works are in progress
Last Updated at : April 2012
755 Power Supply System GTECH-Paul Y. Joint Venture 01/2011 2014 N/A
  Sheung Wan-to-Sai Ying Pun Tunnel Construction
Blasting works were successfully completed. Electrical and mechanical works are in progress
Last Updated at : April 2012
757 Lifts KONE Elevator (HK) Ltd 12/2010 2014 N/A
  Sheung Wan-to-Sai Ying Pun Tunnel Construction
Blasting works were successfully completed. Electrical and mechanical works are in progress
Last Updated at : April 2012
758 Escalators and Moving Walkways KONE Elevator (HK) Ltd 12/2010 2014 N/A
  Sheung Wan-to-Sai Ying Pun Tunnel Construction
Blasting works were successfully completed. Electrical and mechanical works are in progress
Last Updated at : April 2012
759 Main Control System Thales Transport & Security (Hong Kong) Ltd 01/2011 2014 N/A
  Sheung Wan-to-Sai Ying Pun Tunnel Construction
Blasting works were successfully completed. Electrical and mechanical works are in progress
Last Updated at : April 2012
760 Communications, Transmission & Telephone Systems CLPE-SHSI Joint Venture 01/2011 2014 N/A
  Sheung Wan-to-Sai Ying Pun Tunnel Construction
Blasting works were successfully completed. Electrical and mechanical works are in progress
Last Updated at : April 2012
761 Radio System Radio Frequency Engineering Ltd 12/2010 2014 N/A
  Sheung Wan-to-Sai Ying Pun Tunnel Construction
Blasting works were successfully completed. Electrical and mechanical works are in progress
Last Updated at : April 2012
771 Building Services for Sai Ying Pun Station and Hong Kong University Station Gammon E&M Ltd 10/2010 2014 Sai Ying Pun Station and Hong Kong
  Sheung Wan-to-Sai Ying Pun Tunnel Construction
Blasting works were successfully completed. Electrical and mechanical works are in progress
Last Updated at : April 2012
771B Building Services for Kennedy Town Station Chun Wo E&M Engineering Ltd 10/2010 2014 Kennedy Town Station
  Sheung Wan-to-Sai Ying Pun Tunnel Construction
Blasting works were successfully completed. Electrical and mechanical works are in progress
Last Updated at : April 2012
772 Trainborne Signalling Equipment Alstom Hong Kong Ltd. 04/2009 12/2011 N/A
  Sheung Wan-to-Sai Ying Pun Tunnel Construction
Blasting works were successfully completed. Electrical and mechanical works are in progress
Last Updated at : April 2012